Dual-Screen Splicing

Two (2) DirectView LED Displays can be installed together to create one (1) large display.

Standard Installation
Hidden System Control Box Installation
NOTE: The System Control Boxes can be installed under the Cabinets (standard installation) for front access, or behind the Cabinets.

Wall Mounting

Installing the Upper and Lower Wall Mount Brackets

  1. Ensure the wall area and size is an appropriate installation site.
  2. NOTE: The height of the Upper Wall Mount Brackets must not be less than 90 ³⁵/₆₄" (2300 mm) from the ground.
  3. Using the Wall Mount Bracket (pictured above) as a guide, mark at least eight (8) holes and pre-drill them.
  4. Install the first Upper Wall Mount Bracket with the provided screws (M6x50mm Expansion for masonry; TA6x30mm for load bearing wood).
  5. Repeat Step 2, ensuring the second Upper Wall Mount Bracket is level with the first upper bracket. Keep a 3 ¹¹/₃₂" (85 mm) space between the two brackets.
  6. Install the Lower Wall Mount Brackets in the same manner as the Upper Wall Mount Brackets. The distance between the Upper and Lower Wall Mount Brackets is 53 ⁵/₃₂" (1350 mm).
  7. NOTE: You can also install the Upper Wall Mount Brackets, hang the screen, and then install the Lower Wall Mount Brackets for a more precise fit.
    Ensure the wall can safely support 297.62 lbs. (135 kg).
    Ensure the deviation of the wall surface is < ¹³/₆₄" (< 5 mm).
  8. Repeat Steps 1~5 for the second display. Keep a 2 ⁵⁵/₆₄" (72.8 mm) space between the first and second display's Wall Mount Brackets.
  9. After installing both Upper and Lower Wall Mount Brackets of both displays, the installation wall should look like: